Government of Saskatchewan ministries, Crown corporations and organizations are working to minimize the impacts of the postal service disruption.

Les ministères, les sociétés d’État et les organismes du gouvernement de la Saskatchewan travaillent à réduire au minimum les répercussions de l’interruption des services postaux.

Google Translate Disclaimer

A number of pages on the Government of Saskatchewan's website have been professionally translated in French. These translations are identified by a yellow box in the right or left rail that resembles the link below. The home page for French-language content on this site can be found at:

Renseignements en Français

Where an official translation is not available, Google™ Translate can be used. Google™ Translate is a free online language translation service that can translate text and web pages into different languages. Translations are made available to increase access to Government of Saskatchewan content for populations whose first language is not English.

Software-based translations do not approach the fluency of a native speaker or possess the skill of a professional translator. The translation should not be considered exact, and may include incorrect or offensive language. The Government of Saskatchewan does not warrant the accuracy, reliability or timeliness of any information translated by this system. Some files or items cannot be translated, including graphs, photos and other file formats such as portable document formats (PDFs).

Any person or entities that rely on information obtained from the system does so at his or her own risk. Government of Saskatchewan is not responsible for any damage or issues that may possibly result from using translated website content. If you have any questions about Google™ Translate, please visit: Google™ Translate FAQs.

NIPAWIN HYDROELECTRIC STATION UNIT 3 REBUILD BEGINS

Released on May 27, 2004

Work has begun on a complete rebuild of SaskPower's Nipawin Hydroelectric Station unit 3. This is the second phase in a three-year, $23.4 million overhaul of the station's three turbines and generators.

"Through 75 years of operation, SaskPower has provided its customers with cost-effective and reliable power, and the rebuild of unit 3 is in keeping with this long-standing commitment to the people of Saskatchewan," Minister responsible for SaskPower Frank Quennell said. "With significant rebuilds such as this Nipawin project, SaskPower injects millions of dollars annually into local economies, and provides work for suppliers and contractors across Saskatchewan."

The rebuild, which will be completed in December 2004, will improve station reliability and reduce operating costs. Each unit now has to be taken out of service annually for service; when this project is completed, unit maintenance cycle will be reduced to once every three years. The cost to rebuild unit 3 is expected to be $7.5 million.

Saskatchewan workers are scheduled to perform the majority of the on-site work. Hitachi Canadian Industries Ltd. has been contracted to rebuild the massive turbine runner for unit 3 in its Saskatoon facility. Hitachi performed similar work on a rebuild of Nipawin unit 1, which was completed in November 2003.

Located on the Saskatchewan River just west of Nipawin, the Nipawin Hydroelectric Station's three units have a combined generating capacity of 255 megawatts (MW). The first 85 MW unit was commissioned in 1985, and the two additional 85 MW units were commissioned in 1986.

-30-



For More Information, Contact:

Larry Christie
SaskPower
Regina
Phone: (306) 566-3167