Released on July 3, 2001
An 11.7 km section is about to be resurfaced on Highway 5 from Mikado toCanora.
"Road work will begin on this $1 million project this week and should be
completed by mid-July," Highways and Transportation Minister Pat Atkinson
said. "Completion of this job will require an estimated 24 full-time
workers."
Potzus Paving & Road Maintenance Ltd. of Yorkton was awarded this project.
This project is an extension of the 13.1 km resurfacing improvements from
Veregin to Mikado on Highway 5 completed last summer. The 11.7 km section
will begin just outside the town of Canora and will continue to the village
of Mikado.
"Highway 5 has been experiencing higher volumes of heavy traffic recently
and it's a priority to keep this highway in good driving condition,"
Atkinson said. "Once this highway work is finished, motorists will enjoy a
lengthy stretch of improved highway."
Highways and Transportation's budget this year is a record $311.7 million,
which will help to improve the major highway system that carries 65 per
cent of provincial traffic.